Section 2 Classification Survey during Construction


201. General

In the classification survey during construction, the construction, materials, scantlings, and workman- ship of the hull, equipment and machinery are to be examined in detail in order to ascertain that they meet the relevant requirements of the Rules, and for barges which are required to be marked with load lines, the load lines are to be assigned.


202. Submission of plans and documents


1. When it is intended to build a barge for classification, the following plans and documents are to be submitted for approval of the Society before the work is commenced.

(1) Hul1

(A) Midship section

(B) Construction profile

(C) Deck plans (Construction of hold and hatch)

(D) Superstructure end bulkheads

(E) Shell expansion

(F) Single bottoms and double bottoms

(G) Bulkheads

(H) Arrangements to resist panting in both peaks

(I) Skeg constructions

(J) Joint part constructions between pusher and barge

(K) Stability data

(2) Machinery

(A) General arrangement of machinery space

(B) Particulars and sectional assembly of internal combustion engines used as important system

(C) Boilers and pressure vessels: Plans and data specified in Pt 5, Ch 5 of the Rules

(D) Piping diagrams

(E) Arrangement plan and circuit diagram of switchboards (including materials used for main part)

(F) Diagrams of the wiring system including type of cables, normal working Current, and type and rating of protective device

(G) Arrangement of electrical equipment

2. When it is intended to build a barge for classification, other than plans and documents in Par 1,

the following plans and documents are to be submitted for the approval.

(1) General arrangement

(2) Specifications for hull and machinery

(3) In a pontoon barge and a barge with special cargo handling system or special condition of

loading, plans showing the particulars of the cargo intended to be carried and of

(4) Manual of towing or Pusher

(5) Preliminary stability data

(6) Where load lines are intended to be assigned, the following plans in addition to to (D) tn Par 1 (1):

(A) General arrangement

(B) Lines

its distribution


plans from (A)


image

Rules for the Classification of Steel Barges 2015 5

image

Ch 2 Classification Surveys Ch 2


3.


203.


(C) Hydrostatic curves

(D) Plans showing the height of timber deck cargo and the arrangements of lashing and fixing, if the timber load lines are to be assigned

(7) Particulars of machinery

(8) Calculation sheets of torsional vibration for generator shaftings(in case where the maximum con- tinuous output of engine is more than 100 kW)

(9) Calculation sheets of battery capacity for navigation light

Submission of other plans and documents than specified in Par 1 and 2 may be required where deemed necessary by the Society.


Presence of surveyor


1. In the classification survey during construction, inspections are to be carried out covering a1l stages of the work from its commencement until its completion.


2. The presence of the Surveyor is required at the following stages of the work in relation to hull and equipment.

(1) Material test.

(2) When designated by the Society during shop work or sub-assembly.

(3) When each block is assembled.

(4) When hydrostatic test, watertight test, etc. are carried out.

(5) When hull is completed.

3. The presence of the Surveyor is required at the following stages of the work in relation to machinery.

(1) When the tests for boilers and pressure vessels to belong to Group I or Group II are carried out.

(2) When the tests for the valves, cocks and distance pieces attached to the shell plating are carried

out.

(3) When the tests for the explosion-proof type electrical equipments are carried out.

(4) When machinery is installed on the barge.

(5) When the tests and trials on board are carried out.

(6) When the popping test and accumulation test for safety valve of boiler are carried out.

(7) When the test for machinery of special type are carried out.

4. The requirements specified in Par 2 and 3 may be modified having regard to the actual status of facilities, technical abilities and quality control at the works.


5. Submission of the data of the tests carried out in the works as specified in Ch 20, 1601. 2, 4

and 5 may be required where deemed necessary by the Surveyor.


204. Sea trials

For barges having unconventional construction or special navigation system, sea trials will be quired where deemed necessary by the Society.


re-