Section 3 Survey after Construction


301. Survey after construction

In the survey after construction, the actual scantling of main parts of the ROV's are to be meas- ured in addition to such examinations of the construction, materials, workmanship, actual conditions of structure, outfitting, equipment and performance.


302. Submission of plans

In the survey after construction, plans and documents as may be required for classification survey during construction are to be submitted. If plans cannot be obtained, facilities are to be given for the Society's surveyor to take the necessary information from the ROV's.


303. Tests

In the Survey after Construction, the hydraulic pressure tests, water tight tests and performance tests are to be carried out in accordance with the requirements of the Rules. However, these tests may be dispensed with, provided that sufficient data on the previous tests are available.